A supply bond guarantees that a material vendor will deliver the materials named in a supply contract. If the vendor doesn't deliver, the buyer is made whole for the materials it paid for and never received.
Start a Supply Bond ApplicationA supply bond is a contract bond between three parties. The supplier (the principal) buys the bond. The buyer (the obligee), usually the builder, general contractor, or project owner, is the party it protects. The surety company backs the supplier's promise to furnish the materials in the contract.
If a supplier contracted for six custom windows ships five, the buyer can claim against the bond for the sixth. If the surety pays a claim, the supplier repays the surety. A supply bond is a credit guarantee for the buyer, not insurance for the supplier.
Material vendors and manufacturers who furnish materials for a construction project need one when their supply contract says so. If the contract doesn't require a bond, there isn't one to buy. Requirements are most common on:
A performance bond guarantees a contractor finishes the project. A payment bond guarantees the contractor pays its subcontractors and suppliers. A supply bond guarantees neither. It only guarantees that the supplier delivers the materials in its contract, or that the buyer is reimbursed for what wasn't delivered.
The bond amount usually matches the value of the materials in the supply contract. A contract to furnish $500,000 of lumber typically calls for a $500,000 supply bond; a contract for $300,000 of electrical wire calls for $300,000. Check your contract: some buyers set a different percentage.
Each supply contract gets its own bond. One bond can't cover all of a supplier's contracts, and the bond doesn't renew. It ends when the supply contract is complete.
We can't quote a price for a supply bond until the application is complete. The surety sets the premium after reviewing the supplier, the contract, and the materials.
Rising material prices are a common cause of supply bond claims. If lumber, steel, or copper costs jump after the contract is signed, a supplier can be stuck delivering at the old price. An escalation clause tied to a published cost index protects both sides.
The online application takes about 10 minutes. Complete as much of the information as you can so that we can get started; anything you don't have yet, we'll follow up on. After you submit, we email you a copy and a short list of documents to send back.